ERDEMİR EREGLI IRON & STEEL FACT. INC. -AIR SEPERATION
PLANT |
| Specifik
Operation: |
Cold Box Assembly |
| Contractor: |
TAIYO
NIPPON SANSO CORP. |
| Sub
Contractor: |
Ekon
Endüstri İnşaat ve Tic. A.Ş. |
| Date: |
September
2005 |

As per the
agreement between CKV - Ekon, far before the job all preliminary
investigations have been generated. In paralel to these, lifting
and ringing plans and drawings were prepared and submitted to
Ekon & Sanso.
The cold box group was composed
of 3 pieces ;
2 Pieces of
Cold Box Bottom block, 6 x 7 x 24 (H)
m. 100 t.
Top Block 6 x 7 x
35 (H) m. 130 t.
1 Piece of HexBox
7 x 8 x 14 (H) m. 80 t.
The assembly plan
mutually agreed with Sanso & Ekon covered the installation of
Cold box bottom block and hex box and then the cold box top
block.

The cranes
selected and proposed for this project were;
Lifting
Crane; CC2800 Demag (84 m. Main boom)
Tailing
Crane; LT1250 Liebherr (29 m. main boom).
On the other
hand, considering all adverse conditions beyond our controll (weather,
surface conditions intermediate assemlies, etc.) CKV has
proposed the total operation time as 7 days.
Following the prepation
of site base as per our requirements, noting the weather
conditions, on the first day of operations, Coldbox bottom
section and hexbox were installed respectivelly according to the
plans.
Then
after, Ekon carried out the fixation of both blocks within right
time, to shift to next stage.
 

As the wind
was effective especialy in the afternoons, it was decided to
complete the installation of cold box top section before noon.


Then next day, following a
coordinated operation, tihis block was placed succesfully after all these
installations, within a week all the platforms , stairs, etc. have been
assembled with the help of LT1250.
  



|